The project activities for installation of the mono and tower sections included:

- mobilisation crane barge in Rotterdam-NL, transit to and mobilisation in King’s Lynn-UK

- transit to site (The Wash area)

- survey for all activities (crane barge position, mono pile, scour and tower)

- mono pile installation by using vibrator hammer and impact hammer

- during piling Pile Driving Analysis monitoring

- pile fill in with gravel

- scour protection on seabed around pile, 2 layers of big bags (200x)

- installation cathodic protection

- installation of tower section

- grouting tower section to mono pile

- installation top platform

- assistance during installation actual tide gauge

- transit to and demobilisation in Rotterdam-NL